ARCP
ARCP is short for Asbestos Removal Control Plan and all asbestos removers must prepare one of these for any licensed asbestos removal work.
A copy must be given to the PCBU and be available for workers and homeowners while removal is in progress. An ARCP must also be kept and available for 2 years after the work is done.
An ARCP must include:
How the work will be carried out and when,
PPE, machines and equipment used during the project,
Details of the asbestos being removed (eg, how much, the type and location)
A plan showing removal area, air monitoring points, and locations of signs, negative air unit, and decontamination unit.
Details on the waste (transportation and disposed site)
Who will be involved in the removal (supervisors & removal staff)